Context

The system controls physical processes where undetected severe faults can cause hazardous conditions or data corruption.

Trigger

A documented severe fault condition occurs during operation.

Acceptance Criteria

  • In fault-injection tests covering 100% of documented severe fault classes, shutdown starts within 1 s for ≥ 99% of injected faults (safety test report, every release).
  • System reaches the documented safe state within 5 s of shutdown start, accepts zero new commands/transactions, and post-test integrity checks find zero data-corruption incidents (integration + safety test report, every release).
  • Release is blocked within 10 min if either threshold is missed (release gate log).